Octavia Street and Henry Street Reconstruction

Share Octavia Street and Henry Street Reconstruction on Facebook Share Octavia Street and Henry Street Reconstruction on Twitter Share Octavia Street and Henry Street Reconstruction on Linkedin Email Octavia Street and Henry Street Reconstruction link
Aerial photo of Octavia and Henry Street.

Octavia Street (north of Catharine Street) and Henry Street (from Octavia Street to Murney Street) are being reconstructed.

The existing sewer along Octavia Street is a combined sewer (storm and sanitary in the same pipe) and it will be necessary to separate the two by constructing a new storm sewer and replacing the sanitary sewer.


Planned improvements:

  • Installation of a new storm sewer main and catch basins
  • Replacement of the existing sanitary sewer main and the existing sanitary services
  • Replacement of the existing watermain and the existing water services
  • Complete road reconstruction to an urban standard with new concrete curb and gutter, new concrete sidewalk, and new asphalt road surface


These upgrades will ensure safe, reliable municipal water and wastewater services and an efficient transportation system that addresses the needs of our residents and businesses.

Octavia Street (north of Catharine Street) and Henry Street (from Octavia Street to Murney Street) are being reconstructed.

The existing sewer along Octavia Street is a combined sewer (storm and sanitary in the same pipe) and it will be necessary to separate the two by constructing a new storm sewer and replacing the sanitary sewer.


Planned improvements:

  • Installation of a new storm sewer main and catch basins
  • Replacement of the existing sanitary sewer main and the existing sanitary services
  • Replacement of the existing watermain and the existing water services
  • Complete road reconstruction to an urban standard with new concrete curb and gutter, new concrete sidewalk, and new asphalt road surface


These upgrades will ensure safe, reliable municipal water and wastewater services and an efficient transportation system that addresses the needs of our residents and businesses.

  • Construction Commencement

    Share Construction Commencement on Facebook Share Construction Commencement on Twitter Share Construction Commencement on Linkedin Email Construction Commencement link

    The first phase of the Octavia Street and Henry Street Reconstruction project is set to begin Fall 2025. The first phase of work is anticipated to be complete in December 2025 and will consist of the full reconstruction of Henry Street between Murney Street and Octavia Street, as well as work within the intersection of Octavia Street and Henry Street. Traffic control and signage will be in place to direct motorists and pedestrians accordingly.

    The second phase of this project will commence in Spring 2026. Further updates will be provided prior to commencement of the second phase. Full project completion is anticipated by Fall 2026.”

  • Public Consultation Centre Held

    Share Public Consultation Centre Held on Facebook Share Public Consultation Centre Held on Twitter Share Public Consultation Centre Held on Linkedin Email Public Consultation Centre Held link

    A Public Consultation Centre was held May 14, 2025.