Work is actively underway on the rehabilitation of the Upper Front Street Bridge! The following are notable elements currently completed or underway:


Works Completed:

· Removal of Ballast wall and Expansion Joint assemblies at East

· Removal of Interlock Pavers, Curb and Gutter, Concrete under sidewalks at East approach

· Earth excavation at East approach

· Removal of Splash Panels

· Removal of Asphalt and Waterproofing over deck

· Installation of Access Platform at North underside for Tie-Beam/concrete overhang repairs

· Removal of Street Lighting Poles, Removal of Concrete Lamppost Pedestals at Pier

· Removal of Hangers and Temporary Support for Utility at North

· Abrasive blast Cleaning of Concrete Arches

· Removal of Concrete Sidewalk, Curb and Pedestrian Barriers at North

· Partial depth concrete removal at West abutment


Works Ongoing:

· Reconstruction of Overhang Brackets

· Reconstruction of Retaining Wall at NE approach

· Partial depth concrete removal at Arch hangers and ribs


Works Upcoming:

· Reconstruction of North Sidewalk