Work is actively underway on the rehabilitation of the Upper Front Street Bridge! The following are notable elements currently completed or underway:
Works Completed:
· Removal of Ballast wall and Expansion Joint assemblies at East
· Removal of Interlock Pavers, Curb and Gutter, Concrete under sidewalks at East approach
· Earth excavation at East approach
· Removal of Splash Panels
· Removal of Asphalt and Waterproofing over deck
· Installation of Access Platform at North underside for Tie-Beam/concrete overhang repairs
· Removal of Street Lighting Poles, Removal of Concrete Lamppost Pedestals at Pier
· Removal of Hangers and Temporary Support for Utility at North
· Abrasive blast Cleaning of Concrete Arches
· Removal of Concrete Sidewalk, Curb and Pedestrian Barriers at North
· Partial depth concrete removal at West abutment
· Reconstruction of Retaining Wall at NE approach
· Reconstruction of Overhang Floor Brackets under North Sidewalk
- Works Ongoing / Upcoming:
· Reconstruction of Sidewalk and Curb at North (Concrete and PVC conduit installation)
· Installation of Hanger support for conduits at North
· Partial depth concrete repair and Xypex waterproofing at Tie Beams and Overhang Floor Brackets at North, West Abutment and Pier
· Partial depth concrete repair at South Arch hangers and ribs