December 2025 Construction Update

Construction of the New Belleville Agricultural Society Facility is well underway as we approach the end of 2025. A major milestone has been reached as installation of structural steel building components has commenced. The installation of structural steel will continue into early 2026 concurrently with work to complete the building's foundation and the installation of site services such as watermain and sanitary sewer.
The project remains on schedule for an anticipated completion of Summer 2026.