Upper Bridge Rehabilitation

Share Upper Bridge Rehabilitation on Facebook Share Upper Bridge Rehabilitation on X (formerly Twitter) Share Upper Bridge Rehabilitation on Linkedin Email Upper Bridge Rehabilitation link
Aerial photo of the Upper Front Street Bridge.

A design for Front Street (Upper Bridge) is underway for rehabilitation due to structural deterioration.

Addressing these issues now will help preserve this structure that was built in the 1930's and avoid more costly repairs or full replacement in the future.


Planned rehabilitation work includes:

  • Removal and reconstruction of cantilevered sidewalks
  • Removal and reconstruction of curbs
  • Removal and replacement of expansion joints, ballast walls, lighting, conduit, and wiring
  • Partial depth concrete removals on concrete overhang brackets, arch ribs, hangers, tie beams, and floor beams
  • Bridge deck waterproofing and paving


With Lower Bridge now complete, this project is moving towards the construction phase of rehabilitation in 2026.

A design for Front Street (Upper Bridge) is underway for rehabilitation due to structural deterioration.

Addressing these issues now will help preserve this structure that was built in the 1930's and avoid more costly repairs or full replacement in the future.


Planned rehabilitation work includes:

  • Removal and reconstruction of cantilevered sidewalks
  • Removal and reconstruction of curbs
  • Removal and replacement of expansion joints, ballast walls, lighting, conduit, and wiring
  • Partial depth concrete removals on concrete overhang brackets, arch ribs, hangers, tie beams, and floor beams
  • Bridge deck waterproofing and paving


With Lower Bridge now complete, this project is moving towards the construction phase of rehabilitation in 2026.

  • Construction Update - September 2026

    Share Construction Update - September 2026 on Facebook Share Construction Update - September 2026 on X (formerly Twitter) Share Construction Update - September 2026 on Linkedin Email Construction Update - September 2026 link

    Work is actively underway on the rehabilitation of the Upper Front Street Bridge! The following are notable elements currently completed or underway:


    Works Completed:

    · Removal of Ballast wall and Expansion Joint assemblies at East

    · Removal of Interlock Pavers, Curb and Gutter, Concrete under sidewalks at East approach

    · Earth excavation at East approach

    · Removal of Splash Panels

    · Removal of Asphalt and Waterproofing over deck

    · Installation of Access Platform at North underside for Tie-Beam/concrete overhang repairs

    · Removal of Street Lighting Poles, Removal of Concrete Lamppost Pedestals at Pier

    · Removal of Hangers and Temporary Support for Utility at North

    · Abrasive blast Cleaning of Concrete Arches

    · Removal of Concrete Sidewalk, Curb and Pedestrian Barriers at North

    · Partial depth concrete removal at West abutment


    Works Ongoing:

    · Reconstruction of Overhang Brackets

    · Reconstruction of Retaining Wall at NE approach

    · Partial depth concrete removal at Arch hangers and ribs


    Works Upcoming:

    · Reconstruction of North Sidewalk


    Work is actively underway on the rehabilitation of the Upper Front Street Bridge! The following are notable elements currently completed or underway:


    Works Completed:

    · Removal of Ballast wall and Expansion Joint assemblies at East

    · Removal of Interlock Pavers, Curb and Gutter, Concrete under sidewalks at East approach

    · Earth excavation at East approach

    · Removal of Splash Panels

    · Removal of Asphalt and Waterproofing over deck

    · Installation of Access Platform at North underside for Tie-Beam/concrete overhang repairs

    · Removal of Street Lighting Poles, Removal of Concrete Lamppost Pedestals at Pier

    · Removal of Hangers and Temporary Support for Utility at North

    · Abrasive blast Cleaning of Concrete Arches

    · Removal of Concrete Sidewalk, Curb and Pedestrian Barriers at North

    · Partial depth concrete removal at West abutment


    Works Ongoing:

    · Reconstruction of Overhang Brackets

    · Reconstruction of Retaining Wall at NE approach

    · Partial depth concrete removal at Arch hangers and ribs


    Works Upcoming:

    · Reconstruction of North Sidewalk


  • Construction Update - August 2026

    Share Construction Update - August 2026 on Facebook Share Construction Update - August 2026 on X (formerly Twitter) Share Construction Update - August 2026 on Linkedin Email Construction Update - August 2026 link

    Construction on the rehabilitation of the Upper Front Street Bridge has commenced. Urbanlink, the successful contractor awarded the work, has mobilized to site and has begun concrete removals on the approaches and underside of the structure. Traffic control measures are in place and the bridge is fully closed to vehicular and pedestrian traffic. Detours are in place with appropriate signage.

    Construction on the rehabilitation of the Upper Front Street Bridge has commenced. Urbanlink, the successful contractor awarded the work, has mobilized to site and has begun concrete removals on the approaches and underside of the structure. Traffic control measures are in place and the bridge is fully closed to vehicular and pedestrian traffic. Detours are in place with appropriate signage.

  • Construction Commencement

    Share Construction Commencement on Facebook Share Construction Commencement on X (formerly Twitter) Share Construction Commencement on Linkedin Email Construction Commencement link

    The tender for the rehabilitation of the Upper Bridge has been awarded. Construction commencement is anticipated in Summer 2026.

    The tender for the rehabilitation of the Upper Bridge has been awarded. Construction commencement is anticipated in Summer 2026.

  • Tender Closed

    Share Tender Closed on Facebook Share Tender Closed on X (formerly Twitter) Share Tender Closed on Linkedin Email Tender Closed link

    The Tender for the Upper Bridge Rehabilitation has closed and bids are being evaluated

    The Tender for the Upper Bridge Rehabilitation has closed and bids are being evaluated

  • Issued for Tender

    Share Issued for Tender on Facebook Share Issued for Tender on X (formerly Twitter) Share Issued for Tender on Linkedin Email Issued for Tender link

    The Tender for the Upper Bridge Rehabilitation project has been issued with anticipated startup in spring 2026. Construction completion is anticipated by end of 2026.

    The Tender for the Upper Bridge Rehabilitation project has been issued with anticipated startup in spring 2026. Construction completion is anticipated by end of 2026.

  • Public Consultation Centre

    Share Public Consultation Centre on Facebook Share Public Consultation Centre on X (formerly Twitter) Share Public Consultation Centre on Linkedin Email Public Consultation Centre link

    A Public Consultation Centre will be held as follows to provide information and gather feedback regarding the proposed rehabilitation of Front Street (Upper) Bridge.

    Date: Thursday March 19, 2026

    Time: 2:00 p.m. to 4:00 p.m. AND 6:00 p.m. to 8:00 p.m.

    Location: SMB Room (3rd floor) Belleville City Hall, 169 Front Street, Belleville, Ontario

    As no formal presentations will be made, members of the public are encouraged to attend at their convenience. Project staff will be on hand to answer any questions and provide more information. All presentation materials will be available on the City’s Get Involved webpage one week prior to the PCC.

    Any comments or inquiries can be submitted to the Project Manager.

    • Email: construction@belleville.ca

    • Phone: 613-967-3200 ext. 3454

    A Public Consultation Centre will be held as follows to provide information and gather feedback regarding the proposed rehabilitation of Front Street (Upper) Bridge.

    Date: Thursday March 19, 2026

    Time: 2:00 p.m. to 4:00 p.m. AND 6:00 p.m. to 8:00 p.m.

    Location: SMB Room (3rd floor) Belleville City Hall, 169 Front Street, Belleville, Ontario

    As no formal presentations will be made, members of the public are encouraged to attend at their convenience. Project staff will be on hand to answer any questions and provide more information. All presentation materials will be available on the City’s Get Involved webpage one week prior to the PCC.

    Any comments or inquiries can be submitted to the Project Manager.

    • Email: construction@belleville.ca

    • Phone: 613-967-3200 ext. 3454

  • RFPQ has been issued with tender to follow

    Share RFPQ has been issued with tender to follow on Facebook Share RFPQ has been issued with tender to follow on X (formerly Twitter) Share RFPQ has been issued with tender to follow on Linkedin Email RFPQ has been issued with tender to follow link

    An RFPQ has been issued to assess and confirm qualified contractors. A tender to complete the rehabilitation project will follow.

    An RFPQ has been issued to assess and confirm qualified contractors. A tender to complete the rehabilitation project will follow.